SRA1A Project Update - 5.9.19

SRA1A Project Update - 5.9.19  - This project is currently on schedule and is expected to be complete by the end of 2019. The Contractor continues to make steady progress on the work in both Segment 2 and Segment 3. The revetment work on Segment 1 is expected to begin a little later in the project. This week, the Project Team wanted to put some numbers to what has been done so far. The numbers are as of Monday, May 6, 2019.


🔸- Segment 2 (South 22nd Street to South 9th Street) Project Update:

• New Sidewalk: 1,500 square feet installed.
• New Water main: 3,210 linear feet of 12-inch pipe installed, plus 19 gate valves and 5 fire hydrants. The contractor also began moving customers to the new water line this week.
• New Gravity Sewer: 7 sanitary sewer structures and 788 linear feet of 8-inch sanitary sewer line installed. This work is complete.
• French Drain System: 18 new drainage structures, 911 feet of a planned total of 2,081 feet of 30-inch pipe installed, and 765 feet of 36-inch pipe placed. All of the 36-inch pipe is now installed. The work also calls for installation of 4,566 feet of 42-inch pipe.


🔸 - Segment 3 (North 18th Street to Osprey Drive) Project Update:

• New Sand: This work is about 98 percent complete. This week, the contractor has begun moving the sand over the top of the wall and creating the final slope of the dune. Later in the project, vegetation will be planted on the dune.
• Guide Wall Installation: Work has been completed to just north of Marine Drive. Installation will continue to just south of Osprey Drive.
• Secant Wall: Nearly 1,200 of the needed 1,847 auger cast piles have been installed along more than 2,400 linear feet.
• Concrete Cap: More than 300 cubic yards of concrete poured to complete nearly 1,600 linear feet of the wall.