News Flash

Home

14 Stories
Posted on: March 18, 2019

SRA1A Project Update - 3.15.19

 SRA1A Project Update - 3.15.19 

⚠️ South 22nd Street to South 9th Street: The Contractor has begun installing the new water main along the west side of SRA1A. The work began at the south end of the project and is moving its north. Sidewa...

Read on...

Home
Posted on: March 11, 2019

SRA1A Project Update

A1A Update 3.8.19

🔶 SRA1A Project Update 🔶 - Here's this week's status update:

⚠️ North 18th Street to Osprey Drive: The Contractor has begun drilling operations to install the concrete shafts that will create the buried seawall. Work is continuing northward...

Read on...

Home
Posted on: March 7, 2019

**Important Information for residents on A1A concerning trash pick up**

If you are located on State Road A1A within the construction area that is being detoured, please place your trash for pickup in the alleyways. The sanitation department is not able to pick up on A1A in those areas. Thank you.

Read on...

Home
Posted on: March 1, 2019

State Road A1A Update for March 1, 2019

🔶 SRA1A Project Update 3.1.19 🔶 

🔸 Northside 🔸- Next week the Contractor will begin drilling operations to install the concrete shafts that will create the buried seawall. The finished wall will have alternating "colu...

Read on...

Home
Posted on: February 25, 2019

Recycling Update for the City of Flagler Beach

As of February 25, 2019, the City of Flagler Beach will no longer be recycling glass of any kind.

Acceptable items that are still being collected are:

  • Steel, tin and aluminum cans (emptied and rinsed)
  • Cardboard (clean)
  • Magazines, phone books and newspapers
  • Pla...
Read on...

Home
Posted on: February 26, 2019

State Road A1A Update

🔶 SRA1A UPDATE 🔶 - The SRA1A southbound traffic detour onto South Central Avenue will become effective later today and the Project Team is currently installing signage from 7th Street South to 23rd Street South. During this lengthy detour onto South Cen...

Read on...

Home
Posted on: February 14, 2019

Status of Dune Walkovers

A message from: 

Charles Burgan

General Contractor

02/14/19

Status of Dune Walkovers/ beach access for Flagler and Beverly beaches going South to North

Open walkovers- safe for pedestrian use

  • S 28th
  • S 27th
  • S 26th
  • S 25th
  • S 23rd
  • S 20th
  • S 19th
  • S 17th
  • S 8th
  • S 9th
  • S ...
Read on...

List of Dune Walkover Status Home
Posted on: February 14, 2019

State Road A1A Reconstruction Project Update

FDOT

Construction is underway on both Segment 2 (South 22nd Street to South 9th Street) and Segment 3 (North 18th Street to Osprey Drive). Please see updates below.

IMPORTANT: Safety in the Work Zone

It is very important that pedestrians and drivers use caution ...

Read on...

Home
Posted on: February 7, 2019

“Active Scams - Community Alert”

FLAGLER BEACH POLICE DEPARTMENT

204 SOUTH FLAGLER AVENUE • FLAGLER BEACH, FL 32136

(386) 517-2023 • FAX (386) 517-2022

WWW.FBPD.ORG

CHIEF Matthew P. Doughney

Media Release

February 8, 2019

“Active Scams - Community Alert”

The...

Read on...

Home
Posted on: January 4, 2019

Notice - New Building Department Location!

As of Tuesday, January 8, 2019 the City of Flagler Beach Building Department and Planning Department will be at a new location, 800 S. Daytona Avenue Flagler Beach, FL (The Wickline Building).

The Building Department at 800 S. Daytona Ave. will now be the ...

Read on...

Home
Posted on: December 6, 2018

Rebuild Florida Housing Repair and Replacement Program

Rebuild Florida is an assistance program to help repair, rebuild or replace homes damaged by Hurricane Irma.

To help as many Floridians as possible repair and rebuild homes damaged by Hurricane Irma, the deadline to register for assistance from Rebuild Flo...

Read on...

Home